All Pending Development Work on Zarghoon Road and Samungli Road Should Be Completed by December 31: Balochistan High Court

QUETTA (Daily Qudrat Quetta): A two-member bench of the Balochistan High Court, comprising Chief Justice Justice Muhammad Kamran Khan Mulakhail and Justice Muhammad Najamuddin Mengal, while hearing Constitutional Petition No. 824/2016, reviewed the implementation of court orders regarding development projects, sanitation, and debris removal in various areas of the city, including Zarghoon Road and Samungli Road, and directed the relevant authorities to complete all pending work by December 31, 2026.
During the hearing, petitioner Syed Nazeer Agha Advocate appeared in person, while Additional Advocates General Zahoor Ahmed Baloch and Salma Abdul Fattah, counsel for Cantonment Board Quetta Rajesh Nath Kohli, Additional Commissioner (Revenue) Quetta East Hafiz Muhammad Tariq, counsel for Metropolitan Corporation Quetta Izhar-ul-Haq, Nadir Ali Chilgari Advocate, Deputy Project Director Chief Minister Quetta Development Package Abid Mahmood, Superintendent CMPQD Ali Imran, and counsel for the Project Director Zarq Khan Kakar were also present in court.
In compliance with the court’s earlier order dated November 5, 2026, the Deputy Project Director Chief Minister Quetta Development Package presented a progress report regarding the development work of the road from Science College to Hockey Chowk and from there to Akram Hospital and its associated infrastructure. According to the report, the asphalt wearing work on the road has been completed, and the installation of curb stones and pavers has also been completed; however, minor alterations and improvement work remains at some places. The installation of signboards is ongoing, while the installation of gantry boards and streetlights has not yet been completed. Tree plantation and planting of creepers toward the railway is also ongoing.
The report further stated that debris has been removed from Zarghoon Road, while the work of installing safety grills is ongoing, which is expected to be completed in the next three to four days. After the installation of the grills, the plantation work will begin.
On this occasion, an implementation report and photographic evidence were also submitted to the court on behalf of the Metropolitan Corporation Quetta, which confirm the measures taken to remove debris and garbage from Samungli Road and Zarghoon Road.
The Additional Advocate General also submitted the minutes of the meeting to the court, in which it was decided that the Administrator Metropolitan Corporation Quetta and the relevant sanitation departments will ensure regular collection and proper disposal of solid waste, garbage, and other municipal waste from both locations, namely Shahbaz Town Samungli Road and Zarghoon Road in front of Akram Hospital. Waste collection points will be established at these locations, and until a permanent system is devised, a temporary wall or fence will be erected to prevent illegal dumping of garbage and debris.
The meeting also decided that the Deputy Inspector General of Police Quetta, in cooperation with the relevant administration, will ensure the deployment of security personnel at both locations and an effective monitoring and patrolling arrangement, so that no person, contractor, shopkeeper, or private trolley operator can illegally dump debris or solid waste there. Strict action in accordance with the law will be taken against violators. Furthermore, the Special Magistrate Metropolitan Corporation Quetta, the anti-encroachment cell, and relevant police authorities will ensure strict implementation of the court orders.
The court was told that all relevant departments were directed to submit comprehensive implementation reports, including photographic evidence, through mutual contact and cooperation to the office of the Advocate General Balochistan before the next hearing, November 26, 2026.
During the hearing, in response to the court’s inquiry, the Deputy Project Director said that the prescribed deadline for the completion of the Zarghoon Road project was October 31, 2026, which has passed; however, due to the delay in the completion of the project, proceedings to impose a penalty on the relevant contractor are ongoing, the amount of which will be deducted from his final bill.
The court directed the Deputy Project Director to ensure the work of excavation and preparation of flower beds on both sides of the bridge’s protective walls, while all remaining development work of the project, including internal plantation along the road, should be completed in any case by December 31, 2026, or earlier.
The court further ordered that a comprehensive implementation report regarding the completion of all the said works be submitted on December 31, 2026, through the office of the Advocate General Balochistan to the Registrar of the High Court in chambers so that the court can review it.
The court, directing that a copy of its order be sent to the office of the Advocate General Balochistan for necessary information and compliance, adjourned the next hearing to a date to be fixed by the office.