Senate Subcommittee Raises Alarm Over Delays in Balochistan Package, Escalating Project Costs
Gish Kaur Dam cost jumps from Rs11 billion to Rs44 billion; concerns raised over possible impact of Panjgur Dam on local population and technical flaws in recruitment portals

ISLAMABAD: A subcommittee of the Senate Standing Committee on Less Developed Areas has expressed serious concern over delays in projects under the Aghaz-e-Haqooq-e-Balochistan Package and sharp increases in the cost of major development schemes, terming the situation a waste of national resources.
The meeting was held at the Old PIPS Hall, Parliament Lodges, Islamabad, under the convenorship of Senator Jan Muhammad Buleedi.
The Planning Commission briefed the subcommittee on progress under the Balochistan package, informing it that 138 projects were being handled, including more than 133 ongoing schemes and seven new projects, with a total approved cost of Rs1,984.3 billion.
The committee was told that Rs193 billion had been allocated for Balochistan in the current financial year. The water sector includes 18 projects involving dams and canals, while 54 projects relate to road infrastructure, 36 of which are being implemented by the Balochistan government.
Officials from the Ministry of Water Resources informed the committee that 18 water-sector projects had been approved. Of these, 13 are being implemented by the Balochistan government, while five are being executed by WAPDA under the ministry’s supervision.
The combined cost of these projects stands at Rs369.3 billion, with Rs16.9 billion allocated for the current financial year.
Officials further stated that 51 water-related projects had been completed in Balochistan since 2010. Regarding the Mangi Dam, the committee was informed that approximately 80 per cent of the work had been completed and that water from the dam would primarily be used for drinking purposes.
The Balochistan Irrigation Department briefed the subcommittee on 13 dams currently under construction, including Gorak Storage Dam, Awaran Dam, Panjgur Dam, Winder Dam, Shahzainak Dam and Gish Kaur Storage Dam.
Concerns Over Panjgur Dam’s Impact on Local Population
During the briefing on Panjgur Dam, Senator Jan Muhammad Buleedi expressed serious reservations about the project, particularly regarding construction-related disputes and the possible adverse effects of blocking the main river’s water flow on the daily lives of local residents.
He warned that the project could affect the entire population of Panjgur district and directed the relevant authorities to conduct a detailed assessment.
He also stressed the need for reports from the Space and Upper Atmosphere Research Commission (SUPARCO) and WAPDA, directing officials to submit a comprehensive report at the next Senate committee meeting.
Officials informed the subcommittee that consultations had been held with local representatives and arrangements would be made to ensure an adequate flow of water to traditional kareez systems.
However, the convener observed that communities in other parts of Balochistan had also faced difficulties because of similar dam projects. He also expressed concern over the increase in the project’s cost from Rs18 billion to Rs23 billion.
Gish Kaur Dam Cost Rises from Rs11 Billion to Rs44 Billion
The subcommittee also reviewed the Gish Kaur Storage Dam project, with the convener questioning its financial viability and overall benefits.
Senator Buleedi expressed serious concern that the project’s revised cost had increased from Rs11 billion to Rs44 billion, describing the escalation as alarming and a potential waste of national resources.
He questioned whether the project could deliver sufficient benefits in proportion to its substantially increased construction cost.
He also observed that the scheme might not be beneficial for the local population, particularly because there was no significant agricultural land in the surrounding area and some nearby land was already occupied by housing schemes.
The relevant department was directed to reassess the project and present its findings to the subcommittee.
Officials informed the committee that the prevailing law and order situation had made it difficult to complete several dam projects within their original timelines, necessitating extensions in their completion schedules.
Review of Road Infrastructure Projects
Reviewing road infrastructure schemes, National Highway Authority (NHA) officials briefed the subcommittee on ongoing and completed projects in Balochistan.
Referring to the prime minister’s directions regarding road development, Senator Buleedi observed that the Frontier Works Organisation (FWO) generally undertakes projects for which complete funding is available, while avoiding schemes with only partial funding arrangements.
The committee was informed that a private company was working on the Western Bypass in Quetta, while the FWO was executing work on three sections of the N-25 Karachi-Khuzdar highway.
NHA officials stated that 52 per cent of the overall funds had been allocated to Balochistan. They added that the prime minister had directed that the Karachi-Chaman highway project be completed on a priority basis.
The committee was also informed about progress on various road schemes. Around 86 per cent of the Quetta Bypass project has been completed, the access road linked to Reko Diq is nearing completion, and 64 per cent of the Awaran-Hoshab Road project has been completed.
Officials stressed the need for timely release of funds to ensure completion of these projects within their revised schedules.
The convener directed the relevant authorities to summon project directors of the road schemes linking Buleda to Prom, Buleda-Balgatar and Buleda-Jalgi so they could brief the subcommittee on their progress.
He also expressed concern over a road passing through Hub and instructed officials to pay special attention to the Western Quetta Bypass.
More Than 4,500 Vacancies Advertised for Balochistan Candidates
The subcommittee subsequently reviewed employment opportunities and recruitment initiatives for the people of Balochistan.
Officials from the Establishment Division informed the committee that advertisements had been issued for more than 4,500 vacancies under Balochistan’s provincial quota.
They said a special cell had been established within the Establishment Division to monitor and facilitate recruitment-related matters concerning the province.
Officials clarified that although recruitment to Basic Pay Scale (BPS) 1 to 4 positions had generally been restricted and transferred to the private sector, the federal government had exempted Balochistan from this restriction.
Candidates from the province had also been exempted from technical tests and granted a five-year relaxation in the upper age limit.
The committee was further informed that a 10 per cent quota had been reserved for women and five per cent for minorities.
Officials said the Establishment Division secretary had taken up the matter on a priority basis and issued instructions to facilitate candidates from Balochistan.
Senator Flags Technical Problems in Online Recruitment Portals
The convener expressed concern over the appointment of candidates in Pakistan Railways on a contractual basis and stressed the need to consider their regularisation.
He also raised reservations over recruitment advertisements issued by the Finance Division, Pakistan Military Accounts Department, Survey of Pakistan and K-Electric Company (KESCO).
Senator Buleedi highlighted technical problems in online recruitment application systems, pointing out that despite the five-year age relaxation granted to Balochistan candidates, the software did not allow over-age applicants to submit their applications.
He directed the relevant authorities to immediately address these technical shortcomings to ensure that eligible candidates from Balochistan were not deprived of employment opportunities.